Seabed surveys underway at Lillebælt Syd offshore wind project

Apr 10, 2025

After several weeks of seabed surveys in Jammerland Bugt, activities continue with 3D surveys in the waters near the Lillebælt Syd offshore wind project.

The seabed surveys have started at the Lillebælt Syd offshore wind project with one big survey vessel that has started to collect data on water depth and physical conditions of the seabed. That vessel will soon be joined by two smaller vessels. Using advanced 3D technology, the vessels will measure the seabed, identify large rocks and detect old unexploded ordnance etc. This important data collection will be used for the further design process and construction of the wind farm.

Zhanar Dreisig, Asset Manager at TotalEnergies Offshore Wind, is pleased that the work can now continue on for Lillebælt Syd:

“I’m pleased to see the geophysical operations launched now for Lillebælt Syd. The vessels will carry out geophysical surveys that are crucial for the development of the offshore wind farm and our goal of being able to produce electricity in the Lillebælt area from 2029,” she says.

The seabed surveys in Lillebælt are expected to last until the end of July 2025, and particularly the largest of the three vessels will be visible from the coast during that time.

“Geophysical surveys give us insight into the structure of the seabed and ensure that we can plan the construction of wind turbine foundations and the installation of subsea cables with the highest precision and minimal impact on the marine environment,” says Andreas Karhula Lauridsen, Vice President and Head of Offshore Wind at European Energy.

With a capacity of 165 MW, the Lillebælt Syd offshore wind farm will be able to supply more than 148,000 households in 2029, when the farm is expected to be in operation. This is a significant contribution to Sønderborg Municipality’s climate ambition ProjectZero. 

Facts

  • Establishment permit granted: December 2024
  • Expected start of construction: 2027
  • Expected commissioning: 2029
  • Capacity: 165 MW
  • Number of wind turbines: 11 units, each 256 metres tall with a capacity of 15 MW
  • Owners: TotalEnergies (72.25%), European Energy (15%), and SONFOR (12.75%)